Meerwind
The Meerwind Süd I Ost wind farm is located around 23 km north of Helgoland, and consists of a total of eighty wind turbines with a capacity of 3.6 megawatts each supplying up to 360,000 households a year with electricity.
In detail...
• Securing the monopiles on the seabed
• Delivery of offshore filter material to the fall-pipe vessel from our quarry in Jelsa
• Delivery of offshore material from our quarry in Larvik
Facts and figures:
Builder:
Boskalis
Client:
WindMW GmbH
Construction period:
2013
Construction costs:
€1,200 million
Subcontractor:
Stema Shipping A/S and Mibau Baustoffhandel GmbH
Quantity delivered:
Quarter of a million tonnes of filter material and riprap
Purpose:
Scour protection for monopiles